Inter RAO Electric Power Plants Announces Operating Results for the First Quarter of 2020
JSC Inter RAO – Electric Power Plants announces operating results for the first quarter of 2020.
Indicator* |
Q1 2020 |
Q1 2019 |
Change, % |
---|---|---|---|
Installed power generation capacity as at the end of the reporting period, MW |
21672.2 |
22452.4 |
-3.5 |
Installed heat capacity as at the end of the period, thous. Gcal/h |
5601.7 |
5677.7 |
-1.3 |
Electricity output, billion kWh |
19775.6 |
24149.7 |
-18.1 |
Installed capacity utilization factor (ICUF) % |
41.78 |
49.88 |
- |
Heat distribution from collectors, million Gcal |
1691.9 |
1804.5 |
-6.2 |
Fuel mix, % Gas/ coal/ fuel oil |
81.52/18.22/0.25 |
84.48/15.37/0.15 |
-2.96/2.85/0.1 |
*Including JSC Nizhnevartovskaya SDPP, as well as Mayakovskaya TPP, Talakhovskaya TPP and Pregolskaya TPP in the Kaliningrad region.
Power generation by enterprises of JSC Inter RAO — Electric Power Plants in the reporting period amounted to 19.8 billion kWh, having decreased by 18.1% compared to 2019. The decrease is mainly attributed to reduced power consumption in the UES of Russia by 1.2% in comparison with the corresponding period of the previous year (2.3% without taking into account the impact of an additional day in the leap year (February 29)), as well as increased electricity output by hydro power plants (22,5% in comparison with the same period of 2019) due to high water.
The installed capacity utilization factor of JSC Inter RAO — Electric Power Plants decreased to 41.78%.
In the Q1 2020, the installed power plant capacity of JSC Inter RAO – Electric Power Plants decreased by 3.5% compared with the same period of 2019 and amounted to 21.7 GW (in 2019 – 22.6 GW). This indicator was influenced by several factors:
-
commissioning of a power unit of Pregolskaya TPP in Kaliningrad, with the capacity of 115 MW;
-
decommissioning of inefficient equipment of three power units at the Kashirskaya SDPP (totaling 900 MW at both facilities) on January 1, 2020;
-
increased installed capacity of power unit No.2 at Mayakovskaya TPP (+2.65 MW) and power unit No.2 at Talakhovskaya TPP (+2.1 MW) due to recertification since August 1, 2019.
In the first quarter of 2020, despite measures to increase energy efficiency, and along with decommissioning of inefficient equipment, and commissioning of energy-efficient generating equipment, due to a reduction in output by 18.1%, there was growth of specific fuel equivalent consumption for power generation by 0.5 g of specific fuel per kWh.
As a part of the maintenance routine in Q1 2020, the Inter RAO – Electric Power Plants and JSC Nizhnevartovskaya SDPP completed 6 repairs of power units (total power generation capacity of 1 460 MW), 6 repairs of turbo generators (total power generation capacity of 648 MW), and 2 repairs of boiler units (total steam generating capacity of 460 t/h).
Heat distribution by power plants of JSC Inter RAO – Electric Power Plants decreased by 6.2% in comparison with the corresponding period of the previous year and amounted to 1691.9 thousand Gcal. Reduced heat output was related to abnormally warm winter in European Russia.
Inter RAO – Electric Power Plants in Q1 2020
Power Plant |
Electricity, mln kWh |
Heat, thousand Gcal |
||
---|---|---|---|---|
Q1 2020 |
Q1 2019 |
Q1 2020 |
Q1 2019 |
|
Verkhnetagilskaya SDPP |
1 360.6 |
1 592.9 |
63.7 |
70.5 |
Gusinoozyorskaya SDPP |
1151.9 |
1 250.1 |
104.3 |
102.3 |
Dzhubginskaya TPP |
65.1 |
123.7 |
0 |
0 |
Ivanovskiye CPP |
179.6 |
0 |
34.5 |
41.9 |
Iriklinskaya SDPP |
1 003.1 |
1 180.8 |
5.9 |
4.6 |
Kaliningradskaya TPP-2 |
1 257.8 |
1 447.6 |
115.7 |
131.7 |
Kashirskaya SDPP |
189 |
190.3 |
81.8 |
91.1 |
Kostromskaya SDPP |
1 392.6 |
4 514.1 |
65.7 |
73.6 |
Mayakovskaya TPP |
6 |
115.9 |
0 |
0 |
Nizhnevartovskaya SDPP |
3 438.4 |
2 927.4 |
82.1 |
87.6 |
Permskaya SDPP |
2 476.4 |
3 143.9 |
103.7 |
110.1 |
Pechorskaya SDPP |
935.5 |
916 |
91 |
103.2 |
Pregolskaya TPP |
493.8 |
240.9 |
0 |
0 |
Severo-Zapadnaya CHPP |
1 768 |
1 543.2 |
601.6 |
617 |
Sochinskaya TPP |
250.1 |
301.9 |
93.9 |
95.4 |
Talakhovskaya TPP |
25.9 |
131.1 |
0 |
0 |
Urengoyskaya SDPP |
943.8 |
1 028.1 |
28.6 |
32.7 |
Kharanorskaya SDPP |
1 089.9 |
1 051.6 |
48.9 |
46.4 |
Cherepetskaya SDPP |
370.8 |
469 |
47.2 |
53.9 |
Yuzhnouralskaya SDPP |
381 |
419.7 |
123.5 |
142.6 |
Yuzhnouralskaya SDPP-2 |
996.3 |
1 561.5 |
0 |
0 |
TOTAL |
19 775.6 |
24 149.7 |
1 692.1 |
1 804.6 |
The fuel mix of JSC Inter RAO – Electric Power Plants changed insignificantly: the share of natural gas decreased from 84.48% in Q1 2019 to 81.52% in Q1 2020, the share of coal increased by 2.85% – from 15.37% to 18.22%, the share of fuel oil increased by 0.1% and amounted to 0.25%.